FEATURE PROJECTS

Extend Albert Gallatin Ave

from its current terminus at Dobbins Pk to SR-109. The project includes a separated grade interchange at SR-109, new bridge over East Camp Creek, widened bridge over CSX Rail, and signalized intersection at N Blythe Ave.
Map of City where Albert Gallatin Avenue will be extended

Walter Franklin House


100-year old house to be moved from Main Street to the City’s Public Works complex on Long Hollow Pike.  The house will be restored and renovated to become the offices for the City’s Engineering Division.  The new office will include at least 3200 sq-ft of office space, but also may include another 1600 sq-ft of space for traffic signal storage and future traffic operations center.  The move will open up 1250 sq-ft of space in City Hall for relocation of Fire Inspection employees.  $175,000 has been appropriated for design and the building move.  Another $650,000 is in the draft 2017-2018 budget for the restoration/renovation and site development.

ALL CITY PROJECTS

Airport Road Relocation - SIA for Airport


Relocate approximately 1.5 miles of Airport Road to allow for the expansion of the Sumner Regional Airport.
Project is funded by TDOT and Federal Government through a SIA grant and HPP funds; The City has $60,000 appropriated in 16/17 budget to go toward construction costs of paving shoulders.
State managed
Contract for Construction: Hoover, Inc., $5,320,000 to be completed on or before 10/31/2017, but there is a delay expected for weather (Combined with SIA for ABC)

Airport Road Resurfacing / Widening (Coles Ferry Road to Airport) - SIA for ABC


Widen approximately 1.0 mile of Airport Rd to three lanes. This project was initiated by the City because of local industry expansion.
Project is funded by TDOT through a SIA grant. The City has $60,000 appropriated in 16/17 budget to go toward construction costs of paving shoulders
State managed
Contract for Construction: Hoover, Inc., $5,320,000 to be completed on or before 10/31/2017, but there is a delay expected for weather (Combined with SIA for Airport)


Airport Road Resurfacing / Widening (Gregory Drive to Hartsville Pike - SR-25)


Widen approximately 0.5 mile of Airport Rd to three lanes.
Project funded 2016 GO Bond; $500,000
City managed -- expected partial construction by City staff and individualized contractors
Engineer's planning estimate for total project: $500,000
Projected timeline:
February 2017 - In-house survey and design
January 2018 - Begin Construction

Airport Road / Coles Ferry Road Intersection


Improve intersection with turning lanes and installation of new mast arm traffic signal.
Project is funded in 2016 GO Bond; $500,000
City managed -- Rogers Engineering and RGPhillips contracted for design, expected contractor let for construction
Engineer's planning estimate for total project: $500,000
Projected timeline:
November 2016 - June 2017 - Design, Easement/ROW acquisition
July 2017 - Let to Bid
August 2017 - Begin Construction

Airport Road / Gateway Drive Left Turn Lane


Improve intersection with left turn lane on Airport Rd.
Project is funded with $115,000 appropriation in 15/16 budget
City managed -- executing agreement (03/17) with Volkert for design, in-house survey, expected contractor let for construction
Engineer's planning estimate for total project: $115,000
Projected timeline:
February 2017 - Survey - completed 03/02
March through June 2017 - Design
April July 2017 - Let to Bid
May August 2017 - Begin Construction

Albert Gallatin Avenue extension to SR-109


Extend Albert Gallatin Ave from its current terminus at Dobbins Pk to SR-109. The project includes a separated grade interchange at SR-109, new bridge over East Camp Creek, widened bridge over CSX Rail, and signalized intersection at N Blythe Ave.
Project funded by Nashville MPO STP funds (80% from current and past TIP) and local match (20% from 2007 and 2016 GO Bond); $30,615,000; City currently has $6,000,000 available in the 2016 GO Bond ...
City managed -- TDOT Local Programs, Gresham Smith & Partners contracted for design, various consultants for ROW, Smith Seckman Reid for CEI services
Expected total project costs including expenditures, executed contracts, and Engineer's planning estimate for construction: $32,272,000
Projected timeline:
March June 2017 - ROW Certification
June October 2017 - Let to Bid
September 2017 January 2018 - Begin Construction

Big Station Camp Blvd. Corridor Improvements


Widen referenced road in specific and strategic areas from SR-386 to SR-174. Improve various intersections with laneage and signalization.
Corridor Study funded by $40,000 appropriation. Construction and contribution for improvements from Gross Builders (Revere Apartments) for a value of $550,000; City is working with Green Trails for construction and contribution for Carellton Subdivision;
City managed -- Neel-Schaffer contracted for study;
Expected total projects costs: $13,000,000
Projected timeline varies for all portions of the various projects:
Expected to finalize the Big Station Camp Coordior Study for adoption by City Council in 2017


College Street Improvements


Widen, resurface, add stormwater facilities, and construct sidewalks along approximately 1000 LF of roadway of College St.
Project is funded with $140,000 appropriation of which approximately $98,000 remains
City managed -- DDS Engineering design
In-house construction with existing City contractors supplementing; Estimated remaining expenses: $100,000
Expected completion August 2017

Gallatin Industrial Center Expansion on Pase 2 - SIA for Beretta


Construct approximately 2700 LF of new roadway in the Gallatin Industrial Center to allow for the expansion of the Center; especially to serve the Beretta Manufacturing Company.
Project is funded by TDOT through a SIA grant; the City has no financial requirements
State managed
Contract for Construction: Hoover, Inc., $867,000 to be completed on or before 05/31/2017, but there is a delay expected for weather

GreenLea Blvd extension to Long Hollow Pike (SR-174)


Extend and improve the section of GreenLea Blvd north of SR-386 to Long Hollow Pk (SR-174).
Project funded by LIC funds (50% up to $2,000,000 from current and past TIP) and local match (Remainder from general fund, 2014 GO Bond, and developer ); $4,588,000
State Managed
Expected total project costs including expenditures, executed contracts, and Engineer's planning estimate for construction:
Contract for Construction: Brown Builders, Inc., $6,185,000 with an additional $564,000 for TDOT In-house CEI to be completed on or before 11/30/2017

Long Hollow Pike (SR-174) Belvedere Drive Intersection


Improve intersection with additional left turn lane from Belvedere Dr; creating a double-left movement from Belvedere Dr.
Project is funded with $150,000 appropriation in 16/17 budget
City managed -- executing agreement (03/17) with RPM Transportation Consultants for design, in-house survey or consultant, expected contractor let for construction
Engineer's planning estimate for total project: $150,000
Projected timeline:
March 2017 - Survey - completed 04/08
April 2017 - Design
June 2017 - ROW
June August 2017 - Let to Bid
August October 2017 - Begin Construction

Nashville Pike Sidewalk


Construct sidewalk from Lock 4 Rd to Green Wave Dr including pedestrian signalization at signalized intersections.
Project is funded by Congestion Mitigation Air Quality (CMAQ) grant (80%) and local match (20% from special appropriation in 16/17 of $500,000); Total project is $980,000
City managed -- TDOT Local Programs; no consultant contracts at this time
Engineer's planning estimate for total project: $980,000
Projected timeline:
March June 2017 - Execute Local Programs Contract
September 2017 - Environmental
June 2017 March 2018 - Design
November 2017 August 2018 - ROW
June 2018 March 2019 - Let to Bid
September 2018 July 2019 - Begin Construction


Nichols Lane Extension / Drivers Lane Relocation


Construction of approximately 900 LF of roadway to allow Nichols Ln to extend to create a new intersection with Drivers Ln east of SR-109.
Project is funded with approximately $25,000 remaining in the 16/17 budget (originally a $200,000 appropriation) and $900,000 in the 2014 GO Bond.
City managed -- THY for design, survey, contractor let for construction
Engineer's planning estimate for total project remaining: $750,000
Projected timeline:
Design/ Survey and ROW complete
May 2018 - Begin Construction will be coordinated with TDOT project

Safe Routes to Schools Grant (Rucker Stewart Middle Schools - Hancock Street)


Improve pedestrian student access to Rucker Stewart Middle School; construction of a signalized pedestrian crossing at SR-109 and sidewalk on Hancock St to Lock 4 Rd
Project is funded with approximately $225,000 Safe Routes to School Grant; this is a 100% federal/state funded project, the City has no financial requirements
City managed -- TDOT Local Programs, no consultant contracts at this time
Engineer's planning estimate for the total project: $225,000
Projected timeline:
March 2017 - Enviromental
August 2017 - Design
January 2018 - Let to Bid
February 2018 - Begin Construction

St. Blaise Road Underpass Improvements


Improve safety of one-lane underpass of St. Blaise Rd at CSX Railroad by signalization or re-alignment of St. Blaise Rd.
Project is funded with $25,000 appropriation in 15/16 budget
City managed -- in-house survey, design, and constrution depending upon type of improvement
Engineer's planning estimate for total proejct: $55,000
Projected timeline: City Council decision and funding dependent


Traffic Signal Timing and Coordination & ITS Grant


The traffic signal system is being examined and updated for optimization of the signal infrastructure. The CMAQ grant is specifically for the US HWY 31E corridor.
Project is funded with approximately $1,890,000 Congestion Mitigation Air Quality (CMAQ) grant; This is a 100% federal/state funded project; the City has no financial requirements
City Managed -- TDOT Local Programs; no consultant contracts at this time
Engineer's planning estimate for total project: $1,890,000
Projected timeline:
May 2017 - Design
November 2017 - Let to Bid
January 2018 - Begin Construction/Implementation


Various Sidewalks Improvement Grant


Construction of sidewalk in three areas in the City. Boyers Avenue near RT Fisher School, Browns Ln from Starpoint Dr to Nashville Pk (SR-6), and Coles Ferry Rd from S Water Ave to Airport Rd.
Project is funded by Nashville MPO TAP funds (80%) and local match (20% from appropriation $140,000 in 16/17 budget); $700,000
City managed -- TDOT Local programs; no consultant at this time
Engineer's planning estimate for total project remaining: $700,000
Projected timeline:
May 2017 - Design
October 2017 - Let to Bid
December 2017 - Begin Construction

S Water Avenue CSX RR Crossing Improvements


Improvements of S Water Ave at the existing RR Crossing are being proprosed by TDOT through Federal Safety money specified for RR crossing improvements.
Project is funded with federal safety dollars
State managed

S Water Avenue Resurfacing and Widening (Phase 1)


Improvements of S Water Ave between Maple St and Smith St. The ultimate section would be three-lanes with bike lanes and sidewalks.
Project is funded in 2016 GO Bond; $1,500,000
City Managed -- no consultant at this time; expected contractor let project
Engineer's planning estimate for total project: $1,500,000
Projected timeline: none